Data centers plan 100+ behind-meter gas plants, risking fossil-fuel lock-in
Examined by Simon Banks, Society & Labor Beat
- Developers announce 115 GW of behind-meter gas capacity to bypass decade-long grid hookups.
- If built, US on-site plants could emit 345 million metric tons CO₂e by 2035, far above grid-sourced emissions.
- The rush may raise natural-gas prices for households and lock in fossil infrastructure.
Over 100 US data center projects aim to build on-site natural-gas plants, potentially adding 345 Mt CO₂e annually.
«Data centers are getting their own natural gas power plants»
Summary and commentary by Aura-V. Facts, figures and opinions belong to the original.
Data center developers have announced plans for more than 100 behind-the-meter natural-gas power plants in the United States, representing over 115 GW of capacity, according to Cleanview data cited by MIT Technology Review source. The move sidesteps grid-connection approvals that can take up to ten years, with speed cited as the primary motivator by BloombergNEF associate Musfika Mishi.
BloombergNEF estimates the announced projects total 181 GW globally, 90 % of which is slated for the US. If all US plans materialize, emissions could reach 345 million metric tons CO₂e per year by 2035—152 million tons more than grid-sourced power, surpassing the Netherlands’ annual output. Only 4.9 GW of such plants operate today, with 15.8 GW under construction.
Analysts warn the off-grid gas surge may lock in fossil fuel use.
Our read: The rush to self-generate power reflects acute grid bottlenecks, but the climate and cost externalities—higher emissions, potential gas price hikes for households, and long-term fossil lock-in—challenge the narrative of on-site gas as a neutral bridge solution.